Moove Lubrication

Laboratory Fit-Out

Gravesend
Value – £250k
Client – Moove Lubricants
Date – September 2016
Duration – 12 Weeks
Architect – MSHB Associates Architects

Bauvill were appointed to build a new bespoke laboratory which involved stripping out the preexisting work area.

After several design changes, we settled on a scheme which involved installing 2 new fume cupboards and a high-spec AC system which was key to the controlled environment.

As part of our works we installed a priority cupboard system and work surfaces which are common in this type of controlled workspace, as well as bio guard ceiling tiles and grid-work. Vinyl sheet flooring was laid in all areas with cap and cove skirting for easy cleaning.

Bauvill was involved in works to the exterior of the building with a link from one of the adjoining buildings.

The project was handed over on-time and with minimal cost implications.

Bespoke Laboratory Fit-out